Scope:
Buzzard were contracted to install 8no 22t transformers to a solar farm, working in conjunction with a European courier in a remote location with restricted access.
Service:
Full contract lift.
Disciplines:
Appointed person, lift supervisor, slinger/banksman.
Timescale:
Three months in total, all delivered within the customer’s timeframe parameters.
QHSE:
Zero injuries & LTI’s, no environmental issues.