px Group - Holbrook Biomass Turbine Bases.
- No Obligation Quotes
- UK-Wide Coverage
- Fully Insured
- Google ★★★★★
TRUSTED BY
Design Engineering, Full Contract Lift.
Scope:
Buzzard were engaged to jack up a 40t turbine base in order to enable the maintenance team to inspect and install new anti-vibration pads as part of the five yearly maintenance plan.
Buzzard designed several bespoke brackets in order successfully complete the jobs.
Service:
Full contract lift.
Disciplines:
Lifting engineer, appointed person, riggers.
Timescale:
Two weeks, swift engagement was required and delivered as this particular job was outside the original remit.
QHSE:
Zero injuries & LTI’s, no environmental issues.